The rack corridor of a finished MushroomWale grow room, before filling
Environment SOP

Climate Control SOP — Temperature, Humidity, CO₂ and Airflow — India Setup Procedure & Equipment Cost

Mushroom grow room climate control SOP — stage-wise temperature, RH and CO₂ setpoints, airflow and fresh-air design, sensor calibration, costs and PDF.

13 min read9 steps10 parameters
The short answer

Environment SOP — in short

A button mushroom grow room is run to three stage-wise setpoint groups. Spawn run: air 22–24 °C, RH 90–95%, CO₂ 5,000–15,000 ppm, minimal fresh air. Case run: air 24–25 °C, RH 92–95%, CO₂ 5,000–10,000 ppm. Cropping: air 16–18 °C, RH 85–90%, CO₂ below 1,000 ppm with fresh air at roughly 5–8 m³/hour per square metre of bed. Air is delivered through ducting above the racks so that every one of the 7 tiers sees the same conditions.

Why this procedure matters

Climate control is where a mushroom farm either makes or loses its margin. The crop's biological potential is fixed by compost and spawn; the climate system determines how much of that potential is actually harvested, and it does so in a country where ambient temperature swings from 4 °C to 47 °C across the year.

The engineering objective is not to reach a setpoint. It is to hold that setpoint uniformly across a room that is 18 feet wide, has seven tiers of beds, and contains a crop that is generating its own heat and its own CO₂ at a rate that changes daily. A machine that can hit 17 °C but cannot hold ±1 °C across all tiers will produce three different crops in the same room.

This SOP defines the setpoint schedule, the airflow and fresh-air design basis, the sensor and calibration discipline, and the cost structure of the climate package. It reflects the MushroomWale standard build: PUF-panelled rooms with PPGL coating, an AHU per room, Daikin refrigeration as default with Carrier R-404a available on 18×40, 18×60 and 18×70 rooms, ultrasonic humidification and controlled fresh-air blowers.

Step-by-step procedure

  1. 1. Establish the design basis before buying machinery

    Size the plant on peak ambient for your district, not on the annual average. The heat load is the sum of transmission through the PUF envelope, fresh-air load, the crop's own respiration heat, lighting, people and door openings. Under-sizing shows up only in May and June — exactly when the market price is highest — so the buffer belongs in the design, not in the operating manual.

    • Sized on district peak ambient
    • Crop respiration heat included in the load
    • Starting-surge buffer included in DG sizing
  2. 2. Build a sealed, insulated envelope

    Climate control is impossible in a leaky room. Specify PUF panels with PPGL coating on walls and roof, sealed panel joints, insulated doors with functioning gaskets, sealed cable and pipe penetrations, and drain traps that hold water. A room that leaks air also leaks spores and flies in the opposite direction.

    • All joints sealed
    • Door gaskets intact
    • Drain traps water-filled at all times
  3. 3. Install air distribution for 7-tier uniformity

    Deliver conditioned air through overhead ducting with adjustable outlets so air is thrown along the length of the room and returns through the rack spaces. The design target is uniform velocity across every tier without blowing directly onto the beds, which dries caps and causes scaling. Commission the ducting by measuring velocity at the first, middle and last outlet and balancing the dampers.

    • Velocity variation between outlets under 15%
    • No direct airflow onto bed surfaces
  4. 4. Set up sensors and the controller

    Install air temperature, compost temperature, RH and CO₂ sensors per room, with compost probes at three tiers. Set the controller to stage-based recipes rather than manual setpoints, so an operator changing a shift does not change the crop. Log at four-hour intervals minimum; hourly is better and costs nothing once a datalogger is installed.

    • Compost probes at 3 tiers
    • CO₂ sensor per room
    • Automatic logging enabled
  5. 5. Run the spawn run climate stage

    Air 22–24 °C, RH 90–95%, CO₂ 5,000–15,000 ppm, fresh air near zero. Track compost temperature, not air temperature, as the controlling variable, because the crop's self-heating of 2–3 °C is what actually determines whether the mycelium is stressed. Lower the air setpoint progressively from Day 4 as the heat load builds.

    • Compost 24–25 °C, never above 28 °C
    • Fresh air minimal
  6. 6. Run the case run climate stage

    Air 24–25 °C, RH 92–95%, CO₂ 5,000–10,000 ppm. Humidity is the priority here: the casing layer must never dry, and the humidifier should be running in short frequent cycles rather than long ones, which cause wet surfaces and blotch.

    • RH 92–95% held continuously
    • Short humidifier cycles
  7. 7. Execute the airing-down ramp

    Move from case run to cropping over 24–48 hours: air 24 °C to 17–18 °C, CO₂ from above 5,000 ppm to below 1,000 ppm, RH to 88–92%. Fresh-air requirement rises sharply here to roughly 5–8 m³/hour per square metre of bed. This is the peak simultaneous demand on both the refrigeration and the fresh-air system, and it is the load case that should have sized the plant.

    • Controlled ramp, not a step change
    • CO₂ under 1,000 ppm at the end of the ramp
  8. 8. Hold the cropping stage and manage flushes

    Air 16–18 °C, RH 85–90%, CO₂ under 1,000 ppm during flushes. CO₂ and respiration heat peak with each flush and fall between flushes, so the fresh-air fraction should follow the crop rather than sit at a fixed value. Between flushes, RH can be held slightly higher to help the casing recover after watering.

    • Air 16–18 °C ±1 °C across all tiers
    • CO₂ under 1,000 ppm during flush
  9. 9. Weekly maintenance and calibration

    Clean AHU filters weekly, check condensate drainage, verify refrigerant pressures monthly, calibrate CO₂ sensors quarterly against a reference meter, and verify temperature probes against a calibrated thermometer monthly. A drifting CO₂ sensor is the most common invisible cause of a poor pin set, because the controller believes the room is aired when it is not.

    • Weekly filter clean
    • Monthly probe verification
    • Quarterly CO₂ calibration

Operating parameters

ParameterTargetToleranceNote
Spawn run air temperature22–24 °C±1 °CCompost held at 24–25 °C
Spawn run RH90–95%±3%Minimal fresh air
Spawn run CO₂5,000–15,000 ppmup to 20,000High CO₂ is desirable at this stage
Case run air temperature24–25 °C±1 °CSame as spawn run
Case run RH92–95%±3%Highest humidity of the cycle
Cropping air temperature16–18 °C±1 °CLower gives firmer, whiter caps and slower growth
Cropping RH85–90%±2%Above 92% invites bacterial blotch
Cropping CO₂under 1,000 ppm600–1,000 ppmAbove 1,500 ppm gives long stems and open caps
Fresh air during cropping5–8 m³/h per sqm bedvaries with flushPeak demand at airing down and flush peak
Air velocity over bedsgentle circulationno direct impingementDirect airflow causes cap scaling

Daily and per-cycle routine

  • Read and log air temperature, compost temperature, RH and CO₂ every four hours in every room.
  • Walk each room daily and confirm the controller reading against a handheld meter at the far tier.
  • Clean AHU filters weekly and record the date on the unit.
  • Check condensate trays and drain traps weekly for blockage and standing water.
  • Verify temperature probes monthly and CO₂ sensors quarterly against a reference instrument.
  • Record every setpoint change with the reason, the operator and the timestamp — unexplained setpoint drift is a common cause of crop variability.
  • Log DG run hours and any power interruption longer than 15 minutes against the affected rooms.

Cost breakdown

What this workstream costs, how each item is measured, and where it sits in the overall project budget.

ItemCosting basisCost bandNote
PUF panels, walls and roof (PPGL coated)Per sqm of panel areaLargest single equipment block60/80 mm wall thickness; roof panel rated separately
Refrigeration unit per roomPer room by size (18×30 / 18×40 / 18×60 / 18×70 ft)Second largest blockDaikin default; Carrier R-404a available on 18×40, 18×60 and 18×70
AHU, ducting, grilles and dampersPer roomCapitalDetermines tier-to-tier uniformity — do not value-engineer this
Ultrasonic humidificationPer roomCapitalSized on room volume and target RH
Fresh air blowers and filtrationPer roomCapitalSized on 5–8 m³/h per sqm of bed at peak
Sensors and controllerPer roomCapital, moderateAir and compost temperature, RH, CO₂ with logging
Electricals, panels and cablingPer projectCapitalSized on connected load
DG setPer projectCapitalSized on connected load plus starting-surge buffer
Running powerPer unit of electricityLargest recurring operating cost after compostRefrigeration dominates; peak in summer months

Approx. planning guidance only. Live rates follow the current MushroomWale master rate version; quotations carry 5-day validity and a 5% market volatility clause.

GST @ 18% and Transportation are Extra

Civil works, boundary wall, site levelling, land and power sanction are Client Scope. Any additional work demanded beyond the agreed BOQ is treated as extra and charged separately.

Troubleshooting

ProblemLikely causeCorrective action
Temperature differs between top and bottom tiersPoor air distribution or unbalanced dampersRe-balance duct outlets and measure velocity at first, middle and last outlet. Never solve this by lowering the setpoint.
RH will not hold above 85%Undersized humidifier, excessive fresh air, or a leaking envelopeCheck door seals and penetrations first — envelope leakage is the usual cause and no humidifier can overcome it.
CO₂ reading stays flat regardless of fresh airDrifted or failed sensorVerify against a handheld reference meter and recalibrate. A flat reading is almost always instrumentation, not biology.
Long stems and open capsCO₂ too high during croppingIncrease fresh air until CO₂ is reliably below 1,000 ppm during flush peak.
Machine runs continuously and never reaches setpoint in May–JunePlant undersized for peak ambientConfirm against the original load calculation. If the design used average ambient, the room is capacity-limited in summer and needs supplementary cooling.
Water dripping from ducts onto bedsUninsulated duct sections condensingInsulate the affected run and check that condensate trays drain freely.

Records to maintain

Four-hourly climate log per room: air temperature, compost temperature, RH, CO₂
Setpoint change register with reason and operator
Filter cleaning and AHU maintenance log
Sensor calibration certificates and verification dates
Refrigerant pressure and service records
Power interruption and DG run-hour log

How this SOP fits mushroom farming setup in India

Mushroom farming setup in India splits into two halves — what you build, and what you run. The build is the insulated grow room, 7-tier racking, refrigeration, fresh-air handling, power and the packhouse. The run is exactly the set of SOPs in this library. The two are locked together: the setpoints in these procedures decide the machine capacity you must buy, and the bed area decides compost tonnage, spawn quantity and achievable yield.

That is why mushroom farming equipment cost can only be estimated once room size, room count, bed area and the site's peak summer temperature are fixed. Any single "cost per room" number quoted without those inputs is misleading — an 18×30 ft room and an 18×60 ft room differ in panel area, racking metres and machine tonnage, and the same room in a hotter district needs a larger machine to hold 16–18 °C during cropping.

The table below shows how each head is measured, so you can sanity-check any quotation you receive. Live rates follow the current MushroomWale master rate version, quotations carry 5-day validity, and GST @ 18% plus transportation are extra.

Cost headMeasured onWhat drives it
Insulated grow room shell (PUF panels, doors, structure)Per sq ft of built-up room areaThe single largest civil-adjacent head; wall panels 60 mm, roof panels 80 mm, PPGL coated
7-tier MS racking systemPer sq m of bed areaDefines bed area, and therefore compost tonnage, spawn quantity and yield
Refrigeration and air handlingPer room, sized on peak summer loadSized on the location's peak temperature and crop heat load, never on the annual average
Fresh air, ducting and controlsPer roomAir cloth duct, mixing chamber, dampers, sensors and the stage-wise controller profile
Compost unit (wetting slab and Phase-1 bunkers + Phase-2 tunnel)Per tonne of batch capacityOnly for integrated farms; grower-only farms buy Phase-2 or Phase-3 compost instead
Power infrastructure and DG backupPer kVASized with starting surge and diversity factor across rooms
Packhouse and cold roomPer sq ft + per TRPre-cooling to 2–4 °C within 30 minutes is what protects 5–7 day shelf life
For an itemised BOQ against your own room size and district, use the instant quotation tool.

Equipment catalogue

Buy every item used in this SOP

One page with the image, working specification, HSN code, minimum order quantity and live price for each SKU — with a direct buy button. GST and transportation extra.

Browse the full equipment catalogue GST invoice on every order Pan-India dispatch

Download this SOP as a printable PDF

Full procedure, parameter table, cost breakdown, troubleshooting and record sheet — formatted for the farm noticeboard. No form required.

Free expert review

Applying this SOP on your own farm?

Send your details and our project engineer will review your SOP fit, share an itemised cost sheet for your farm size and answer questions on WhatsApp — free.

SOP read: Climate Control SOP — Temperature, Humidity, CO₂ and Airflow (Environment)

Frequently asked questions

The company behind the build

Why Choose MushroomWale

  1. 01

    Engineering Expertise

    Agrimotion Engineering Private Limited is a registered EPC company (CIN U43900UP2023PTC185328, GSTIN 09AAZCA0158R1ZP) based in Firozabad, Uttar Pradesh.

  2. 02

    Proven Track Record

    Turnkey mushroom projects from a 2-room starter to a 20-room commercial farm.

  3. 03

    Bank-Recognized DPRs

    Bank-format DPRs prepared to NABARD, NHB and MIDH norms for loan and subsidy applications.

A MushroomWale grow room in crop, bags on every tier
Start your project

Ready to Build Your Mushroom Farm?

Get a free site survey and a custom quote within 24 hours.

  • Turnkey farms built
  • Pan-India delivery
  • Bank-ready DPR